Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-178-15-07 02-2C3704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-SHA-5-15.4/R16.2 Federal Project: NONE Progress payment No. 03 Payment period ending: 06-20-07 BLAISDELL CONSTRUCTION INC P O BOX 49345 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 551,889.75 3,600.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 551,889.75 3,600.00 5. Mobilization 6. Total Work Completed 551,889.75 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -27,414.49 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 27,414.49 27,414.49 9. Total pay to Contractor 541,889.75 21,014.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,014.49