Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 12-094-16-40 02-2C4604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-MOD-139-34.0/50.6 Federal Project: NH-P139(20) Progress payment No. 09 Payment period ending: 01-27-12 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,445,882.76 -111,375.00 2.a. Extra Work 92,256.55 92,256.55 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 16,538,139.31 -19,118.45 5. Mobilization 850,000.00 0.00 6. Total Work Completed 17,388,139.31 7. Deductions -26,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 17,362,139.31 -29,118.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -29,118.45