Dept. of Trans. FINAL Serial No. Contract No. 12-233-10-24 02-2C4604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-MOD-139-34.0/50.6 Federal Project: NH-P139(20) Progress payment No. 11 Payment period ending: 01-27-12 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,445,882.76 0.00 2.a. Extra Work 92,256.55 0.00 b. Adjustment Comp. 1,883,107.63 0.00 3. Materials on Hand 4. Earned Subject to Retention 18,421,246.94 0.00 5. Mobilization 850,000.00 0.00 6. Total Work Completed 19,271,246.94 7. Deductions 0.00 26,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,271,246.94 26,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,000.00