Dept. of Trans. PROGRESS Serial No. Contract No. 10-328-08-54 02-2C50U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 84% 100% 02-TEH-5-R22.2/R27.5 Federal Project: SARR-058(336) A-058(336) Progress payment No. 16 Payment period ending: 11-19-10 C C MYERS INC 3286 FITZGERALD ROAD RANCHO CORDOVA CA 957426811 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,933,012.10 2,411,474.18 2.a. Extra Work 301,644.82 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 25,234,656.92 2,411,474.18 5. Mobilization 950,000.00 0.00 6. Total Work Completed 26,184,656.92 7. Deductions -27,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 26,157,656.92 2,411,474.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,411,474.18