Dept. of Trans. PROGRESS Serial No. Contract No. 06-355-10-24 02-2C5504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 63% 02-LAS-139-0.6/40.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 12-20-06 NORTHERN CALIFORNIA PAVING P O BOX 1231 YREKA CA 96097 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 919,404.06 0.00 2.a. Extra Work 13,502.36 13,502.36 b. Adjustment Comp. 78,854.41 78,854.41 3. Materials on Hand 4. Earned Subject to Retention 1,011,760.83 92,356.77 5. Mobilization 6. Total Work Completed 1,011,760.83 7. Deductions 8. a.Contract Retentions -50,588.04 -4,617.84 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 961,172.79 87,738.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 87,738.93