Dept. of Trans. PROGRESS Serial No. Contract No. 08-023-14-15 02-2C74U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 36% 02-SHA-5-1.9/R19.0 Federal Project: NONE Progress payment No. 08 Payment period ending: 01-18-08 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,161,410.63 0.00 2.a. Extra Work 113,487.20 9,888.54 b. Adjustment Comp. -1,773.00 -1,773.00 3. Materials on Hand 4. Earned Subject to Retention 7,273,124.83 8,115.54 5. Mobilization 675,000.00 0.00 6. Total Work Completed 7,948,124.83 7. Deductions -46,200.00 0.00 8. a.Contract Retentions -363,656.24 -405.78 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,538,268.59 7,709.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,709.76