Dept. of Trans. PROGRESS Serial No. Contract No. 08-142-09-31 02-2C74U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 55% 02-SHA-5-1.9/R19.0 Federal Project: NONE Progress payment No. 11 Payment period ending: 05-20-08 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,321,484.98 35,074.75 2.a. Extra Work 125,073.17 0.00 b. Adjustment Comp. -1,773.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,444,785.15 35,074.75 5. Mobilization 675,000.00 0.00 6. Total Work Completed 8,119,785.15 7. Deductions -51,200.00 0.00 8. a.Contract Retentions -372,239.26 -1,753.74 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,696,345.89 33,321.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 33,321.01