Dept. of Trans. PROGRESS Serial No. Contract No. 08-201-12-42 02-2C74U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 52% 02-SHA-5-1.9/R19.0 Federal Project: NONE Progress payment No. 13 Payment period ending: 07-18-08 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,991,315.63 424,686.80 2.a. Extra Work 125,073.17 0.00 b. Adjustment Comp. -1,773.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 8,114,615.80 424,686.80 5. Mobilization 675,000.00 0.00 6. Total Work Completed 8,789,615.80 7. Deductions -60,700.00 -9,500.00 8. a.Contract Retentions -405,730.79 -21,234.34 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,323,185.01 393,952.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 393,952.46