Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-340-16-15 02-2C8804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-TEH-36-15.2/15.8 Federal Project: ACST-P036(85) PH-P036(85) Progress payment No. 04 Payment period ending: 11-14-07 JURIN CONSTRUCTION INC P O BOX 1434 WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 682,101.23 275,565.14 2.a. Extra Work 25,204.71 25,204.71 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 707,305.94 300,769.85 5. Mobilization 6. Total Work Completed 707,305.94 7. Deductions -32,000.00 -30,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 675,305.94 270,769.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 270,769.85