Dept. of Trans. PROGRESS Serial No. Contract No. 12-170-08-36 02-2C9504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 28% 02-SIS-96-R0.0/12.0 Federal Project: STPP-960(50E) Progress payment No. 01 Payment period ending: 06-14-12 R BROWN CONSTRUCTION COMPANY INC P O BOX 406 WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 193,602.65 193,602.65 2.a. Extra Work 2,716.27 2,716.27 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 196,318.92 196,318.92 5. Mobilization 101,250.00 101,250.00 6. Total Work Completed 297,568.92 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 297,568.92 297,568.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 297,568.92