Dept. of Trans. PROGRESS Serial No. Contract No. 11-168-13-23 02-2E0004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 53% 60% 02-PLU-70-17.2/17.4 Federal Project: HSST-P070(125) P-P070(125) Progress payment No. 04 Payment period ending: 06-16-11 KNIFE RIVER CONSTRUCTION 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 752,210.00 281,048.00 2.a. Extra Work 17,293.55 15,180.88 b. Adjustment Comp. 2,975.00 2,975.00 3. Materials on Hand 4. Earned Subject to Retention 772,478.55 299,203.88 5. Mobilization 6. Total Work Completed 772,478.55 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 772,478.55 299,203.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 299,203.88