Dept. of Trans. PROGRESS Serial No. Contract No. 09-323-14-39 02-2E1404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 58% 02-SIS-5-R51.1/R58.1 Federal Project: NONE Progress payment No. 02 Payment period ending: 11-19-09 RON HALE CONSTRUCTION INC P O BOX 795 SHASTA LAKE CA 96019 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 844,733.13 41,728.73 2.a. Extra Work b. Adjustment Comp. -3,262.50 -3,262.50 3. Materials on Hand 4. Earned Subject to Retention 841,470.63 38,466.23 5. Mobilization 6. Total Work Completed 841,470.63 7. Deductions -13,262.50 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 828,208.13 28,466.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 28,466.23