Dept. of Trans. PROGRESS Serial No. Contract No. 12-235-09-00 02-2E2004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 67% 02-TRI-299-19.2/19.6 Federal Project: HSNH-P299(166) Progress payment No. 05 Payment period ending: 08-20-12 R BROWN CONSTRUCTION CO INC P O BOX 406 WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 429,120.59 237,705.98 2.a. Extra Work 28,331.22 8,011.22 b. Adjustment Comp. 3. Materials on Hand 18,646.75 18,646.75 4. Earned Subject to Retention 476,098.56 264,363.95 5. Mobilization 52,250.00 11,000.00 6. Total Work Completed 509,701.81 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 528,348.56 275,363.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 275,363.95