Dept. of Trans. PROGRESS Serial No. Contract No. 12-297-10-21 02-2E2004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 55% 86% 02-TRI-299-19.2/19.6 Federal Project: HSNH-P299(166) Progress payment No. 08 Payment period ending: 10-18-12 R BROWN CONSTRUCTION CO INC P O BOX 406 WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 604,957.69 41,360.00 2.a. Extra Work 49,595.52 5,265.03 b. Adjustment Comp. 3. Materials on Hand 18,646.75 0.00 4. Earned Subject to Retention 673,199.96 46,625.03 5. Mobilization 55,000.00 0.00 6. Total Work Completed 709,553.21 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 723,199.96 41,625.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 41,625.03