Dept. of Trans. PROGRESS Serial No. Contract No. 11-144-12-39 02-2E2604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 91% 02-TRI-299-26.1/36.9 Federal Project: NONE Progress payment No. 04 Payment period ending: 05-20-11 PAVEMENT COATINGS CO 10240 SAN SEVAINE WAY MIRA LOMA CA 91752 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 922,599.75 79,094.80 2.a. Extra Work 19,371.84 19,371.84 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 941,971.59 98,466.64 5. Mobilization 6. Total Work Completed 941,971.59 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 941,971.59 98,466.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 98,466.64