Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 16-221-15-53 02-2E2914 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 02-SIS-96-R0.0/77.5 HSTP-P096(51) Progress payment No. 023 Payment period ending: 06-14-16 SANTA MARGARITA CONSTRUCTION CORP. PO BOX 357 TEMPLETON CA 93465 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,110,183.10 -66,145.58 2. a. Extra Work 176,403.66 0.00 b. Adustment Comp. 6,100.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 6,292,686.76 -66,145.58 5. Mobilization 620,000.00 0.00 6. Total Work Completed 6,912,686.76 7. Deductions -81,170.76 -72,646.24 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,831,516.00 -138,791.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -138,791.82