Dept. of Trans. PROGRESS Serial No. Contract No. 15-169-12-59 02-2E3504 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 87% Location: Federal Project: 02-TRI-299-0.4/0.8 HSNH-P299(175) Progress payment No. 013 Payment period ending: 06-20-15 STEELHEAD CONSTRUCTORS INC P O BOX 997 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,331,766.08 61,532.00 2. a. Extra Work 24,405.98 2,917.56 b. Adustment Comp. 3. Materials on Hand 174,132.42 -6,855.00 4. Earned Subject to Retention 1,530,304.48 57,594.56 5. Mobilization 370,500.00 0.00 6. Total Work Completed 1,726,672.06 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -7,759.46 -5,759.46 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,893,045.02 51,835.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 51,835.10