Dept. of Trans. PROGRESS Serial No. Contract No. 21-259-14-42 02-2E4804 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 99% Location: Federal Project: 02-SIS-96 B1ST-X093(9) Progress payment No. 031 Payment period ending: 09-20-21 GOLDEN STATE BRIDGE INC 3701 MALLARD DR BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,425,921.62 160,021.51 2. a. Extra Work 657,241.10 -50.00 b. Adustment Comp. 167,864.00 8,602.00 3. Materials on Hand 4. Earned Subject to Retention 16,251,026.72 168,573.51 5. Mobilization 1,750,000.00 0.00 6. Total Work Completed 18,001,026.72 7. Deductions -30,000.00 -30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 17,971,026.72 138,573.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 138,573.51