Dept. of Trans. PROGRESS Serial No. Contract No. 11-265-11-13 02-2E7104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 38% 02-LAS-395-94.0/96.0 Federal Project: NONE Progress payment No. 01 Payment period ending: 09-20-11 DIG IT CONSTRUCTION INC P O BOX 494 CHESTER CA 96020 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 716,374.80 716,374.80 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 716,374.80 716,374.80 5. Mobilization 6. Total Work Completed 716,374.80 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 716,374.80 716,374.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 716,374.80