Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 22-130-16-12 02-2J1404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 02-TRI-36-0.0/29.0 NONE Progress payment No. 012 Payment period ending: 03-11-22 J.F. SHEA CONSTRUCTION INC. PO BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 68,000.00 68,000.00 2. a. Extra Work 21,910,718.90 1,084,200.58 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 21,978,718.90 1,152,200.58 5. Mobilization 6. Total Work Completed 21,978,718.90 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,968,718.90 1,142,200.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,142,200.58