Dept. of Trans. PROGRESS Serial No. Contract No. 25-296-09-20 02-2J2204 PROGRESS PAYMENT VOUCHER %complete: %time: 36% 12% Location: Federal Project: 02-VAR SNHG-000C(567) Progress payment No. 002 Payment period ending: 10-20-25 HIGHWAY SPECIALTY COMPANY INC PO BOX 141 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 486,288.53 409,313.53 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 228,939.87 31,916.89 4. Earned Subject to Retention 715,228.40 441,230.42 5. Mobilization 47,500.00 10,000.00 6. Total Work Completed 533,788.53 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 762,728.40 451,230.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 451,230.42