Dept. of Trans. PROGRESS Serial No. Contract No. 26-233-14-56 02-2K2104 PROGRESS PAYMENT VOUCHER %complete: %time: 14% 45% Location: Federal Project: 02-TEH-36-R89.0/91.5 NONE 02-TEH-172-5.4/8.9 Progress payment No. 001 Payment period ending: 08-20-26 DIG IT CONSTRUCTION INC. PO BOX 494 CHESTER CA 96020 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 232,691.00 232,691.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 232,691.00 232,691.00 5. Mobilization 6. Total Work Completed 232,691.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 232,691.00 232,691.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 232,691.00