Dept. of Trans. PROGRESS Serial No. Contract No. 04-237-14-16 02-3016U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 90% 02-PLU-70-3.0/7.0 Federal Project: STP-P070(74) ACBH-P070(74) AC-P070(74) Progress payment No. 24 Payment period ending: 08-20-04 AMERICAN CIVIL CONSTRUCTORS WEST COAST INC 3701 MALLARD DR BENICIA CA 94510 Escrow No. 02016 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,384,937.66 783,581.10 2.a. Extra Work 907,762.90 82,537.46 b. Adjustment Comp. 101,000.00 0.00 3. Materials on Hand 78,494.00 15,644.00 4. Earned Subject to Retention 14,472,194.56 881,762.56 5. Mobilization 2,000,000.00 0.00 6. Total Work Completed 16,393,700.56 7. Deductions -20,000.00 -10,000.00 8. a.Contract Retentions -723,609.73 -44,088.13 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,728,584.83 827,674.43 10. Reduction Amt to Escrow 11. Payment to Escrow 723,600.00 12. Net Pymt. this Estimate 827,674.43