Dept. of Trans. PROGRESS Serial No. Contract No. 06-325-15-29 02-311204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 14% 02-SIS-161-18.7/19.3 Federal Project: ACST-P161(2) P-P161(2) ACBR-P161(2) Progress payment No. 03 Payment period ending: 11-20-06 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 368,782.70 167,302.50 2.a. Extra Work 10,690.00 3,602.78 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 379,472.70 170,905.28 5. Mobilization 286,000.00 286,000.00 6. Total Work Completed 665,472.70 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 665,472.70 456,905.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 456,905.28