Dept. of Trans. PROGRESS Serial No. Contract No. 05-024-16-23 02-325804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 75% 58% 02-LAS-44-0.0/14.7 Federal Project: ACNH-P044(40) Progress payment No. 12 Payment period ending: 01-20-05 HAT CREEK CONSTRUCTION AND MATERIALS INC 24339 HIGHWAY 89 BURNEY CA 96013 Escrow No. 02157 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,533,832.52 0.00 2.a. Extra Work 256,702.79 2,905.14 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 7,790,535.31 2,905.14 5. Mobilization 330,090.00 0.00 6. Total Work Completed 8,120,625.31 7. Deductions -11,665.46 1,000.00 8. a.Contract Retentions -389,526.77 -145.26 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,719,433.08 3,759.88 10. Reduction Amt to Escrow 11. Payment to Escrow 389,380.00 12. Net Pymt. this Estimate 3,759.88