Dept. of Trans. PROGRESS Serial No. Contract No. 02-324-15-07 02-3259U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 12% 16% 02-PLU-70-41.5/46.3 Federal Project: ACST-P070(77) P-P070(77) STPL-5909(65) Progress payment No. 02 Payment period ending: 11-20-02 BALDWIN CONTRACTING COMPANY INC 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 666,048.64 355,064.68 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 666,048.64 355,064.68 5. Mobilization 194,000.00 194,000.00 6. Total Work Completed 860,048.64 7. Deductions 8. a.Contract Retentions -66,604.86 -35,506.46 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 793,443.78 513,558.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 513,558.22