Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 08-028-20-51 02-328024 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-SHA-273-R16.7/17.0 Federal Project: 02-SHA-299-23.8/R24.4 NH Progress payment No. 06 Payment period ending: 01-03-08 TULLIS INC P O BOX 493416 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,184,538.72 0.00 2.a. Extra Work 33,554.63 3,207.17 b. Adjustment Comp. -5,422.40 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,212,670.95 3,207.17 5. Mobilization 235,000.00 0.00 6. Total Work Completed 1,447,670.95 7. Deductions -29,000.00 91,530.06 8. a.Contract Retentions -60,473.19 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 60,473.19 60,473.19 9. Total pay to Contractor 1,418,670.95 155,210.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 155,210.42