Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 00-258-16-03 02-347004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-TRI-299-0.0/25.8 Federal Project: ACST-P299(122) PH-P299(122) Progress payment No. 04 Payment period ending: 09-01-00 R BROWN CONSTRUCTION COMPANY INC P O BOX 406 WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 344,436.92 31,191.03 2.a. Extra Work 9,661.74 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 354,098.66 31,191.03 5. Mobilization 16,681.40 0.00 6. Total Work Completed 370,780.06 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -16,145.38 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 16,145.38 16,145.38 9. Total pay to Contractor 360,780.06 37,336.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 37,336.41