Dept. of Trans. PROGRESS Serial No. Contract No. 07-138-14-56 02-347104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 89% 02-SIS-96-65.2/65.6 Federal Project: ACST-P096(46) P-P096(46) Progress payment No. 10 Payment period ending: 05-18-07 STEWART ENGINEERING INC P O BOX 990010 REDDING CA 96099 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,375,557.51 162,384.26 2.a. Extra Work 24,157.34 9,352.08 b. Adjustment Comp. 97,843.98 -1,305.58 3. Materials on Hand 4. Earned Subject to Retention 1,497,558.83 170,430.76 5. Mobilization 150,000.00 0.00 6. Total Work Completed 1,647,558.83 7. Deductions -1,000.00 -1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,646,558.83 169,430.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 169,430.76