Dept. of Trans. PROGRESS Serial No. Contract No. 06-144-14-02 02-359404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 25% 27% 02-LAS-395-R5.8/9.0 Federal Project: NONE Progress payment No. 02 Payment period ending: 05-19-06 MEYERS EARTHWORK INC P O BOX 493730 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 723,358.70 594,698.70 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 723,358.70 594,698.70 5. Mobilization 270,000.00 270,000.00 6. Total Work Completed 993,358.70 7. Deductions 8. a.Contract Retentions -72,335.87 -59,469.87 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 921,022.83 805,228.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 805,228.83