Dept. of Trans. PROGRESS Serial No. Contract No. 08-301-08-20 02-359904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 82% 02-SIS-97-L0.0/0.2 Federal Project: ACST-000C(290) P-000C(290) ACST-000C(290) Progress payment No. 15 Payment period ending: 10-20-08 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,189,463.79 299,374.16 2.a. Extra Work 118,286.27 4,180.68 b. Adjustment Comp. 33,710.31 -37,413.13 3. Materials on Hand 4. Earned Subject to Retention 6,341,460.37 266,141.71 5. Mobilization 586,000.00 0.00 6. Total Work Completed 6,927,460.37 7. Deductions -20,402.60 824.90 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,907,057.77 266,966.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 266,966.61