Dept. of Trans. PROGRESS Serial No. Contract No. 06-326-11-21 02-3603U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 74% 02-MOD-395-11.0/23.8 Federal Project: ACNH-P395(212) ACST-P395(212) PE-P395(212) Progress payment No. 10 Payment period ending: 11-20-06 EAGLE PEAK ROCK AND PAVING INC P O BOX 879 ALTURAS CA 96101 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,587,780.03 249,890.45 2.a. Extra Work 137,070.66 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 8,724,850.69 249,890.45 5. Mobilization 440,235.00 0.00 6. Total Work Completed 9,165,085.69 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,155,085.69 249,890.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 249,890.45