Dept. of Trans. SEMI-FINAL Serial No. Contract No. 07-064-18-31 02-360604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-SHA-89-21.3/26.5 Federal Project: NONE Progress payment No. 09 Payment period ending: 12-20-06 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 960494519 Escrow No. 02220 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,548,883.24 2,500.00 2.a. Extra Work 295,684.12 73,294.42 b. Adjustment Comp. 153,083.41 -12,564.86 3. Materials on Hand 4. Earned Subject to Retention 7,997,650.77 63,229.56 5. Mobilization 725,000.00 0.00 6. Total Work Completed 8,722,650.77 7. Deductions -25,000.00 22,000.00 8. a.Contract Retentions -383,066.68 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 383,066.68 0.00 9. Total pay to Contractor 8,697,650.77 85,229.56 10. Reduction Amt to Escrow -383,060.00 0.00 11. Payment to Escrow 383,060.00 12. Net Pymt. this Estimate 85,229.56