Dept. of Trans. PROGRESS Serial No. Contract No. 14-356-14-01 02-360704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 72% 02-SHA-299-30.3/40.7 Federal Project: STP-P299(176) Progress payment No. 13 Payment period ending: 12-18-14 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,948,921.78 252,678.25 2.a. Extra Work 372,612.34 177,741.33 b. Adjustment Comp. -202,409.33 -202,409.33 3. Materials on Hand 4. Earned Subject to Retention 19,119,124.79 228,010.25 5. Mobilization 2,150,000.00 0.00 6. Total Work Completed 21,269,124.79 7. Deductions -8,000.00 -6,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 21,261,124.79 222,010.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 222,010.25