Dept. of Trans. PROGRESS Serial No. Contract No. 15-023-11-11 02-360704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 72% 02-SHA-299-30.3/40.7 Federal Project: STP-P299(176) Progress payment No. 14 Payment period ending: 01-20-15 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,125,758.20 176,836.42 2.a. Extra Work 432,703.82 60,091.48 b. Adjustment Comp. -201,113.33 1,296.00 3. Materials on Hand 4. Earned Subject to Retention 19,357,348.69 238,223.90 5. Mobilization 2,150,000.00 0.00 6. Total Work Completed 21,507,348.69 7. Deductions -8,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 21,499,348.69 238,223.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 238,223.90