Dept. of Trans. PROGRESS Serial No. Contract No. 15-055-11-48 02-360704 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 80% Location: Federal Project: 02-SHA-299-30.3/40.7 STP-P299(176) Progress payment No. 015 Payment period ending: 02-20-15 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,132,170.74 6,412.54 2. a. Extra Work 446,001.54 13,297.72 b. Adustment Comp. -199,047.61 2,065.72 3. Materials on Hand 4. Earned Subject to Retention 19,379,124.67 21,775.98 5. Mobilization 2,150,000.00 0.00 6. Total Work Completed 21,529,124.67 7. Deductions -1,000.00 7,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,528,124.67 28,775.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 28,775.98