Dept. of Trans. PROGRESS Serial No. Contract No. 05-326-13-57 02-361804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 67% 68% 02-LAS-44-14.5/ .0 Federal Project: ACNH-P044(41) HG-P044(41) Progress payment No. 14 Payment period ending: 11-18-05 HAT CREEK CONSTRUCTION AND MATERIALS INC 24339 HWY 89 N BURNEY CA 96013 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,773,819.56 12,780.78 2.a. Extra Work 100,805.39 0.00 b. Adjustment Comp. 40,889.06 0.00 3. Materials on Hand 4,618.91 0.00 4. Earned Subject to Retention 1,920,132.92 12,780.78 5. Mobilization 6. Total Work Completed 1,915,514.01 7. Deductions -20,539.50 -3,249.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,899,593.42 9,531.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,531.78