Dept. of Trans. PROGRESS Serial No. Contract No. 08-142-11-21 02-362004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 33% 43% 02-SIS-5-R25.6/ .0 Federal Project: ACIM-005-9(166) G-005-9(166) Progress payment No. 04 Payment period ending: 05-20-08 P N P CONSTRUCTION INC 4500 YANKEE HILL CT NO A ROCKLIN CA 95677 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 763,113.74 315,735.39 2.a. Extra Work 10,301.00 0.00 b. Adjustment Comp. -22,501.49 -22,501.49 3. Materials on Hand 4. Earned Subject to Retention 750,913.25 293,233.90 5. Mobilization 6. Total Work Completed 750,913.25 7. Deductions -8,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 742,913.25 288,233.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 288,233.90