Dept. of Trans. PROGRESS Serial No. Contract No. 08-204-12-46 02-362004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 69% 86% 02-SIS-5-R25.6/ .0 Federal Project: ACIM-005-9(166) G-005-9(166) Progress payment No. 06 Payment period ending: 07-18-08 P N P CONSTRUCTION INC 4500 YANKEE HILL CT NO A ROCKLIN CA 95677 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,565,660.94 453,898.34 2.a. Extra Work 102,438.26 92,137.26 b. Adjustment Comp. -22,501.49 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,645,597.71 546,035.60 5. Mobilization 6. Total Work Completed 1,645,597.71 7. Deductions -18,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,627,597.71 536,035.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 536,035.60