Dept. of Trans. PROGRESS Serial No. Contract No. 08-301-08-44 02-362004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 90% 02-SIS-5-R25.6/ .0 Federal Project: ACIM-005-9(166) G-005-9(166) Progress payment No. 09 Payment period ending: 10-20-08 P N P CONSTRUCTION INC 4500 YANKEE HILL CT NO A ROCKLIN CA 95677 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,169,467.53 36,075.00 2.a. Extra Work 102,438.26 0.00 b. Adjustment Comp. -22,501.49 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,249,404.30 36,075.00 5. Mobilization 6. Total Work Completed 2,249,404.30 7. Deductions -15,000.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,234,404.30 46,075.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 46,075.00