Dept. of Trans. PROGRESS Serial No. Contract No. 05-265-13-24 02-364104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 76% 02-TRI-3-6.5/ .0 Federal Project: ACST-P003(28) P-P003(28) ACBR-P003(28) Progress payment No. 15 Payment period ending: 09-20-05 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,487,963.15 642,033.75 2.a. Extra Work 25,167.02 1,379.87 b. Adjustment Comp. -11,141.04 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,501,989.13 643,413.62 5. Mobilization 450,000.00 22,500.00 6. Total Work Completed 2,951,989.13 7. Deductions -0.40 -0.02 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,951,988.73 665,913.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 665,913.60