Dept. of Trans. PROGRESS Serial No. Contract No. 06-024-12-58 02-364104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 82% 81% 02-TRI-3-6.5/ .0 Federal Project: ACST-P003(28) P-P003(28) ACBR-P003(28) Progress payment No. 19 Payment period ending: 01-20-06 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,333,761.95 44,795.40 2.a. Extra Work 76,151.52 8,000.61 b. Adjustment Comp. -11,141.04 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,398,772.43 52,796.01 5. Mobilization 450,000.00 0.00 6. Total Work Completed 3,848,772.43 7. Deductions -0.40 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,848,772.03 52,796.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 52,796.01