Dept. of Trans. PROGRESS Serial No. Contract No. 07-115-11-32 02-3705U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 4% 0% 02-SHA-299-50.7/51.9 Federal Project: ACST-P299(151) PH-P299(151) Progress payment No. 02 Payment period ending: 04-20-07 STEVE MANNING CONSTRUCTION INC P O BOX 491660 REDDING CA 96049 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 243,526.74 236,216.74 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -152,180.63 4. Earned Subject to Retention 243,526.74 84,036.11 5. Mobilization 6. Total Work Completed 243,526.74 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 243,526.74 84,036.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 84,036.11