Dept. of Trans. PROGRESS Serial No. Contract No. 14-143-09-34 02-374304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 83% 100% 02-TRI-299-23.3/ .0 Federal Project: ACNH-P299(168) Progress payment No. 09 Payment period ending: 05-21-14 STEWART ENGINEERING INC P O BOX 990010 REDDING CA 96099 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 697,587.95 180,929.95 2.a. Extra Work 43,546.55 0.00 b. Adjustment Comp. 1,840.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 742,974.50 180,929.95 5. Mobilization 94,700.00 0.00 6. Total Work Completed 837,674.50 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 827,674.50 180,929.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 180,929.95