Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 07-102-11-40 02-374604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 40% 17% 02-PLU-70-49.2/ .0 Federal Project: NONE Progress payment No. 06 Payment period ending: 03-20-07 K M F CONSTRUCTION P O BOX 5486 SHASTA LAKE CA 96089 Escrow No. 02263 Total Estimate This Estimate 1. Contract Itms Without Mobil. 667,402.00 75,560.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 667,402.00 75,560.00 5. Mobilization 6. Total Work Completed 667,402.00 7. Deductions 8. a.Contract Retentions -33,370.10 -434.22 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 634,031.90 75,125.78 10. Reduction Amt to Escrow 11. Payment to Escrow 33,370.00 12. Net Pymt. this Estimate 75,125.78