Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 05-243-08-39 02-375004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-TRI-299-36.1/36.4 Federal Project: ACST-P299(146) PH-P299(146) Progress payment No. 05 Payment period ending: 08-12-05 R BROWN CONSTRUCTION COMPANY INC P O BOX 406 WILLOW CREEK CA 95573 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 710,985.01 177,240.25 2.a. Extra Work 90,157.43 29,506.15 b. Adjustment Comp. -9,504.67 2,444.43 3. Materials on Hand 4. Earned Subject to Retention 791,637.77 209,190.83 5. Mobilization 70,000.00 0.00 6. Total Work Completed 861,637.77 7. Deductions -12,802.62 -12,802.62 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 848,835.15 196,388.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 196,388.21