Dept. of Trans. PROGRESS Serial No. Contract No. 16-078-13-22 02-378904 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 100% Location: Federal Project: 02-SHA-5-R39.5/R40.8 ACBR-058(337) NH-058(337) Progress payment No. 077 Payment period ending: 03-20-16 TUTOR-SALIBA CORP 15901 OLDEN ST SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 96,375,570.15 1,780,790.42 2. a. Extra Work 2,093,138.39 31,594.72 b. Adustment Comp. 1,448,008.21 90,799.76 3. Materials on Hand 378,779.84 -103,091.95 4. Earned Subject to Retention 100,295,496.59 1,800,092.95 5. Mobilization 10,736,352.00 0.00 6. Total Work Completed 110,653,068.75 7. Deductions -3,620,222.44 -88,004.65 8. a. Contract Retentions b. Unsatisfactory Retentions -180,009.30 -180,009.30 c. Reduction after 95% Comp. 9. Total pay to Contractor 107,231,616.85 1,532,079.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,532,079.00