Dept. of Trans. PROGRESS Serial No. Contract No. 16-174-08-57 02-378904 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 100% Location: Federal Project: 02-SHA-5-R39.5/R40.8 ACBR-058(337) NH-058(337) Progress payment No. 080 Payment period ending: 06-20-16 TUTOR-SALIBA CORP 15901 OLDEN ST SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 100,866,314.82 1,194,516.70 2. a. Extra Work 2,399,991.24 153,133.49 b. Adustment Comp. 1,736,193.35 17,873.60 3. Materials on Hand 60,738.45 0.00 4. Earned Subject to Retention 105,063,237.86 1,365,523.79 5. Mobilization 10,736,352.00 0.00 6. Total Work Completed 115,738,851.41 7. Deductions -3,854,101.71 -73,768.40 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 111,945,488.15 1,291,755.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,291,755.39