Dept. of Trans. SEMI-FINAL Serial No. Contract No. 07-047-13-52 02-381114 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-SIS-5-R11.4/R16.0 Federal Project: ACIM-005-9(164) Progress payment No. 10 Payment period ending: 11-15-06 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 96049-4519 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,121,330.56 0.00 2.a. Extra Work 182,319.80 17,090.79 b. Adjustment Comp. -57,555.76 0.00 3. Materials on Hand 4. Earned Subject to Retention 12,246,094.60 17,090.79 5. Mobilization 900,000.00 0.00 6. Total Work Completed 13,146,094.60 7. Deductions -35,685.26 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 13,110,409.34 27,090.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,090.79