Dept. of Trans. FINAL Serial No. Contract No. 11-297-14-51 02-381504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 02-SIS-5-R40.1/R58.1 Federal Project: NONE Progress payment No. 13 Payment period ending: 12-19-06 J F SHEA CONSTRUCTION INC P O BOX 494519 REDDING CA 960494519 Escrow No. 02219 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,945,589.82 0.00 2.a. Extra Work 181,633.39 0.00 b. Adjustment Comp. 55,558.69 43,200.00 3. Materials on Hand 4. Earned Subject to Retention 5,182,781.90 43,200.00 5. Mobilization 500,000.00 0.00 6. Total Work Completed 5,682,781.90 7. Deductions 8. a.Contract Retentions -247,522.23 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 247,522.23 0.00 9. Total pay to Contractor 5,682,781.90 43,200.00 10. Reduction Amt to Escrow -247,520.00 0.00 11. Payment to Escrow 247,520.00 12. Net Pymt. this Estimate 43,200.00